Construction Update
Construction Update
Woodstock- Hartland NH FPAV (50)
US Route 4 Paving Project
DATE: Friday, September 2, 2022
TRAFFIC IMPACT AND DURATION: There are no planned traffic impacts throughout the project limits for the week of September 5 through September 9.
CONSTRUCTION ACTIVITIES: Crews plan to return to the project area to continue work during the week of September 12.
LOCATION:
Woodstock-Hartland NH FPAV(50): Beginning on US Route 4 near Sawyer Road and continuing for approximately 3.1 miles, ending at the intersection of US Route 4 and Vermont Route 12 in Hartland.
PROJECT COMPLETION: Fall 2022
Contact Information:
Name – Delia Makhetha
Phone – 603-263-8881
Email – [email protected]