Construction Update

Woodstock- Hartland NH FPAV (50)

US Route 4 Paving Project

DATE: Friday, November 4, 2022

 

TRAFFIC IMPACT AND DURATION: Monday, November 7 through Friday, November 11, between 7 a.m. and 6 p.m., motorists can expect possible intermittent single-lane closures with alternating one-way traffic. Flaggers will be in place to assist motorists.

 

CONSTRUCTION ACTIVITIES: Crews will continue working on punch list items and possible guardrail repairs throughout the project limits.

LOCATION:

Woodstock-Hartland NH FPAV(50): Beginning on U.S. 4 near Sawyer Road and continuing for approximately 3.1 miles, ending at the intersection of U.S. 4 and VT 12 in Hartland.

 

PROJECT COMPLETION: Fall 2022

 

Contact Information:

Name – Delia Makhetha

Phone – 603-263-8881

Email – [email protected]